CONSTRUCTION ACTIVITIES – 2017
Ministry Funded Projects

Total Population:    31,929                   Total Families:       8,224             Total Hectare: 1,347 Ha

Region Main Activity No of Unit Allocation (Mn.)
Nuwara Eliya Housing 55                                    55.00
Galle Latrine 10                                      0.67
Nuwara Eliya other infrastructure                                      0.49
Nuwara Eliya Road 8                                    27.22
Nuwara Eliya Up play grounds and wire net 3                                      3.99
Nuwara Eliya UP. Community Centre 4                                      8.57
Galle Upgrading CDC 1                                      1.09
Nuwara Eliya Water Supply 3                                      1.28
Galle Re-Roofing 10                                      0.45
Total                                    98.76

 

Early Childhood Development Project (ECDP) Activities

Region Activity No of Unit Allocation (Rs.)
Galle Renovation Play Area 01 250,000.00
Nuwara Eliya Renovation Play Area 01 250,000.00
Nuwara Eliya Renovation Play Area 01 250,000.00
Galle New Play Area 01 350,000.00
Nuwara Eliya Renovation CDC 01 1,300,000.00
Nuwara Eliya New CDC 01 6,500,000.00
TOTAL     8,900,000.00

 

 Status of the Existing Projects

Housing

Region Estate Division Units Allocation (Mn.) Remark
N’Eliya Fernlands Kaipukelle 20                 20.00 5 Not Commenced,8 Walls & slab, 5 Internal Plastering, 2 External Plastering, 5 Floor Rendering Plinth Work
N’Eliya Sheen Upper Punduloya 35                 35.00 15 Up to DPC Level, 05 Floor Concreting, 10 Roof Complete,5 Floor Rendering
Total 55                    55.00

 

Latrine

Region Estate Division Units Allocation (Mn.) Remark
Galle Lelwala Lower 10                  0.67 100%
Total 10                      0.67

Other Infrastructure Activities

Region Estate Division Units Allocation (Mn.) Remark
N’Eliya Dunsinanne Dunsinane School ,Boundary Fence                      0.49 20%

Roads

Region Estate Division Units Allocation (Mn.) Remark
N’Eliya Meddecombra Hospital 1 16.30 Approval Received on 01/08/2017
N’Eliya Dunsinanne Upper 1 0.48 100%
N’Eliya Dunsinanne Lower 1 0.48 100%
N’Eliya Sheen Upper Punduloya 1 0.30 20%
N’Eliya North Punduloya Upper 1 0.50 100%
N’Eliya Ferlands Harrow Lower 1 0.50 100%
N’Eliya  Ferlands Harrow Upper 1 0.50 100%
N’Eliya North Medakubura New Clearing 1 1.46 100%
N’Eliya Fernlands Fernlands 1 0.50 100%
  Total 9 21.02

 

Upgrading Playgrounds

Region Estate Division Units Allocation (Mn.) Remark
N’Eliya Meddacombara Top 1 1.48 85%
N’Eliya Meddacombara Top 1 1.51 85%
N’Eliya South Medakumbura New Middle 1 1.07 Estimate Received,Approval not received
Total 3 4.06

 

Upgrading Community Centres

Region Estate Division Units Allocation (Mn.) Remark
N’Eliya Meddacombara Top 1 1.48 85%
N’Eliya Meddacombara Top 1 1.51 85%
N’Eliya South Medakumbura New Middle 1 1.07 Estimate Received,Approval not received
Total 3 4.06

 

Upgrading Child Development Centres

Region Estate Division Units Allocation (Mn.) Remark
Galle Lelwala Upper 1 1.09 20%

Water Projects

Region Estate Division Units Allocation (Mn.) Remark
N’Eliya Sheen upper 1                  1.03 20%
N’Eliya North Medakubura Upper 1                  0.50 Approval Received 27/10/2017
Total 2 1.53

Re-Roofing

Region Estate Division Units Allocation (Mn.) Remark
Galle Lelwala Upper 6                  0.27 Sheets Handed over
Galle Lelwala Lower 4                  0.18 Sheets Handed over
Total 10                      0.45